Why I've always sucked at software estimation

Looking back at my career, is clear to me that most of the time I failed miserably when estimating software delivery dates. Worse of all is that my estimations are usually underestimations. And this can be really painful. You try hard to keep up with your word and live in chaos near the deadline and afterwards. When you’re the manager this problem amplifies because you’re conditioning others to your predicament. But what is the root of the problem? It’s not like I’ve been dishonest, neither I lack efficiency or focus. And yet I still think that my predictions are accurate in some sense.

Not long ago I realized that what I’ve been doing as an estimator is estimating the time needed to develop something. Not the time necessary to put it on production. And turns out that there is a HUGE difference between both.

I’ll call the time needed to build something construction time. There are clear aspects that one can fail in estimating construction time. Some examples are: not realizing that the problem is NP-Complete while trying to build a deterministic solution or failing to account the time needed to learn something necessary. And good software estimators have to have a good grasp of that. I do.

But there are much more things beyond construction time for you to get a proper production date. Some that come to mind:

  • Failures on the stack infrastructure (when you do not own it)
  • The time you need to wait to someone to review your changes
  • Any changes that might happen in the review loop
  • Meetings that appears in the middle of journey, unexpected personal appointments
  • Something you find in the middle of your progress that you find useful to discuss

I’m no good at estimating any of those, and I dare to bet that no one is. So I think there’s a mismatch of what people can actually predict and what people expect when they get an estimation.

But, how to solve this conundrum?

One might fix that by simply adding a “chunk” of time extra to the estimations. Like the heuristic of: always double your estimation cost. But this solution don’t resonate to me. First, this does not seem honest. And in a way I’m rejecting my analysis and putting some arbitrary time frame that I have absolute no idea of what it represents.

I think the best solution is a re-framing of the answer. We have to make clear what we actually mean by predicting that a given piece of software will take a certain amount of time to be completed.

Talking in terms of hours instead of dates is a better way of putting things. Instead of saying this piece of software will be delivered Monday is much more useful to say this piece of software will demand 8 hours of uninterrupted attention to be constructed. You might very well only get those 8 hours on Wednesday.

This way you don’t compromise yourself with a deadline that might make you miserable and yet convey the sense cost of building x. This approach also adds the benefit of revealing possible problems in the process. If you only got 8 hours of uninterrupted work in 5 days ahead there’s a high probability that something is dysfunctional with yourself or your work environment.

Many people might be unsatisfied by an estimation in terms of construction time instead of production date. But my experience is that the most reasonable stakeholders will understand the situation (and appreciate your clarification and honesty). What they really want is a sense of cost, and when you deliberately give it terms of a date you’re setting a trap for yourself. It’s much better to have an accurate sense of cost instead of a dreamy deadline.

I hope this reflection might help you next time you’re tempted to give an estimation in terms of dates. And if you have additional insights on how not to suck at software estimation please share in the comments.